Once sod is placed, the contractor maintains the watering for 30 days from the date of placement.
October 19-20
Completing addition of sand and gravel along 63rd Avenue in preparation for curb and gutter next week.
Preparing Phase 3 for sprinkler and sod work.
Working on scheduling for the remainder of Phase 3 work. Rain has made this difficult. The goal is to have almost everything wrapped up by the end of October.
Week of October 23
Sprinkler and sod work in Phase 3.
End of October/ early November
City recommends scheduling irrigation system wintering for the end of October or early November.